Agency Appropriately Assessed a Weakness to a Past Performance Reference that was Nine Months Behind Schedule; Bodell Construction Company, GAO B-419213, B-419213.2

30
Protest objecting to agency’s past performance evaluation and conduct of discussions is denied. The protester complained that it had been unreasonably penalized for submitting a past performance project that had not been completed. GAO found the weakness was warranted because in addition to being incomplete, the referenced project had exceeded proposed costs and was nine […]