Protester Can’t Challenge Awardee’s Post-Award Transition Plan; Mission1st Group, Inc., GAO B-4129369.2

35
Protest challenging various aspects of the evaluation is denied. The protester alleged the awardee took exception to the solicitation because its post-award staffing plan did not satisfy solicitation requirements. GAO, however, reasoned that challenges to an awardee’s compliance with transition-related requirements raise matters of contract administration that are not considered in a bid protest. The […]