Agency Not Required to Evaluate Qualifications of Alternate Key Personnel; Mainstream IP Solutions, GAO B-418722

27
Protest challenging the agency’s technical evaluation is denied. The protester contended that the agency had erred in finding that its proposed site manager did not have three years of experience managing telecommunications operations. GAO, however, found the protester had misinterpreted the three-year requirement. The requirement mandated that the manager have a total of 36 months […]