Contractor Obtains the Wrong Permit, Has to Redo the Work and Eat the Loss; Sarro & Associates, Inc. v. United States, COFC No. 19-691C

56
Government’s motion to dismiss for failure to state a claim is granted. The contractor obtained the wrong type of construction permit, and the government ordered the contractor to redo the project. The contractor alleged that the government had breached by requiring the contractor to comply with local permitting requirements. The court disagreed, reasoning that the […]