Courts, Boards, & GAO
Trending Now
It Looked Like the Contractor Destroyed Evidence. Why Did the COFC Hold Not Impose Sanctions? • Court Rejects Protester’s Claims That Air Force Ignored Corruption in Iraqi Sole-Source Award • ASBCA Converts Default Termination to Termination for Convenience: What Government Contractors Need to Know About Jaxon Construction, Inc. • When Key Personnel Leave: The Federal Contractor’s Disclosure Dilemma • GAO Finds That Challenge to Agency’s Failure to Comply With DFARS Requirement Comes Too Late
GAO Finds Meritorious Protest Grounds Intertwined With Non-Meritorious Grounds Entitling Protester to All Its Protest Costs; WorldWide Language Resources, Inc. – Costs, GAO B-417015.6
Get daily insights on bid protests, CDA claims, and contract litigation that shape the GovCon landscape with our Protests & Claims newsletter, delivering up-to-the-minute intelligence Monday–Saturday — Subscribe here.