Signed Contract Modification Terminating Contract Precludes Recovery of Alleged Performance Costs; ASBCA No. 61096, Appeal of Ruby Emerald Construction Company

18
Appeal of the agency’s denial of a claim seeking contract termination costs is denied, where the appellant signed a contract modification terminating the contract at no cost to the government and attesting that it had incurred no costs. Ruby Emerald Construction Company appealed the cancelation of its contract for the purchase of crushed gravel. The […]